Seven men can complete a work in 12 days. They started the work and after 5 days, two men left In how many days will the work be completed by the remaining men

  • 8 Days
  • 9.8 days
  • 6.8 days
  • 5.8 days
Seven men can complete a work in 12 days. They started the work and after 5 days, two men left In ho