16 men and 10 women together can complete a project in 10days. If 12 women can complete the project in 25 days, in how many days 10 men complete the same project

  • 28
  • 24
  • 18
  • 26
  • 10
  • Explanation:

    Let the work will be completed in x days.

    According to question, 

    (16M+10W)×10 = 12W×25

    160M+100W=300W

    160M=200W

    4M=5W

    ∴10 men = 50/4 Women

    Again, according to question,

    25×12=50/4×x

    x= 24 days