P and Q can finish a work in 15 and 10 days respectively. Q starts the work and leaves it after 5 days. The number of days in which P can complete the work is :

  • 6 ½ days
  • 7 ½ days
  • 8 days
  • 9 days
  • None of these
  • Explanation:

    P's 1 day's work = 1/15

    Q's 1 day's work = 1/10

    Q's 5 day's work = 5/10 = 1/2

    So, P can do the remaining work in 15/2 days.

    ∴ Required days = 7 ½ days