If 13 men can complete a piece of work in 36 days, then in how many days will 18 men complete the same work?

  • 16 days
  • 20 days
  • 26 days
  • 30 days
  • None of these
If 13 men can complete a piece of work in 36 days, then in how many days will 18 men complete the sa