A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job?

  • 6 days
  • 30 days
  • 36 days
  • 21 days
 A and B together can do a piece of work in 12 days and A alone can complete the work in 18 day