    A project manager hired 16 men to complete a project in 38 days. However, after 30 days, he realized that only 5/9th of the work is complete. How many more men does he need to hire complete the project on time

  • 48
  • 24
  • 32
  • 16
  • 36
  • Explanation:

    By formula 

    M1×D1/W1 = M2×D2/W2

    16×30÷5/9=M2×8÷4/9

    M2 = 48

    Required men = 48-16 = 32