    In how many days can ‘B’ alone complete the work 

    I. A, B and C together can complete the work in 3 9/13 days

    A and B together can complete the work in 4 4/5 days. B

    And C together can complete it in 6 6/7 days

    II. A,  B and C together can compete the piece of work in 

    3 9/13 days. A and C together can complete the work in 5 1/3 days.

  • If the data in statement I alone are sufficient to answer the question while the data in statement II are not sufficient to answer the question.
  • If the data in statement II alone are sufficient to answer the question while the data in statement I are not sufficient to answer the question.
  • If the data either in statement I alone or statement II alone are sufficient to answer the question.
  • If the data both statements I and II together are not sufficient to answer the question.
  • If the data in both statement I and II are necessary to answer the question.
  • Explanation:

    From statement I,

    (A+B+C)'s 1 day's work =13/48

    (A+2B+C)'s 1 day's work

    =5/24+7/48= 10+7/48=17/48

    ஃ B's 1 day's work= 17/48-13/48= 4/48=1/12

    ஃ Required time = 12days

    From statement II,

    (A+B+C)'s day's work= 13/48

    (A+C)'s 1day's work =3/16

    ஃ B's 1day's work =13/48-3/16=13-9/48

    =4/48=1/12

    ஃ Required time = 12days